احداث سیستم دوم بارگیری کنسانتره به قطار در مجتمع سنگ آهن چادرملو

    • کارفرما:شرکت معدنی و صنعتی چادرملو
    • پیمانکار:شرکت فکور صنعت
    • طراحی پایه
    • طراحی تتفصیلی
    • مهندسی خرید
    • Feeding the loading station silo by belt conveyor Operation capacity of iron ore concentrate: 2500 t/hr
    • Storage of 1000 tones of Iron ore in steel rectangle silo.
    • Train loading via weighing bin by four mushroom valves, operating capacity: 4500 t/hr
    • Record and report the loading data and history based on client’s requirements
    • Molasses spraying on loaded material on train for covering and stabilizing the concentrate

    • Bin
    • Hopper
    • Belt Conveyor
    • Loading valves
    • Loading bins
    • Hydraulic system 